Ask a question
Tell us what you want to understand. We’ll help find the answer or point you to the right information.
Ask a question →Incentives and Campaigns
Omaha Public Power District (OPPD) is finalizing its 2026 Integrated System Plan (ISP).
OPPD is public power. Public input is part of what happens next.
Learn what’s in the plan, what’s changing, and how to get involved.
OPPD’s plans have changed more than once. Deadlines moved, electricity needs grew rapidly, and North Omaha Coal Station (NOS) stayed in service longer than planned.
The board approves a plan to retire North Omaha Coal Station Units 1–3 and convert Units 4–5 from coal to natural gas. Coal operations are expected to end by 2023.
OPPD stops burning coal in Units 1-3, but keeps them available to run on natural gas.
OPPD delays the transition when replacement generation is not ready on schedule. It points to delays in the Southwest Power Pool approval process, and Units 4 and 5 remain on coal longer than originally planned.
OPPD approves plans for more generation and storage as electricity demand grows. The Nebraska Power Review Board questions why the looming need for more generation is not showing up more clearly in their formal plans.
Customer demand keeps growing and the Southwest Power Pool requires utilities to keep more power available in reserve.
The board authorizes spending above the operating plan, citing accelerated near-term generation costs, completion of Turtle Creek and Standing Bear Lake gas plants, and higher costs while purchasing power during unplanned outages.
Management cites growth in demand, an increase in reserve requirements, and slow approval processes from Southwest Power Pool as reasons why North Omaha Coal Station is still needed. At the same time, public opposition grows, with residents and advocates calling on OPPD to end coal use and raising concerns about health, transparency, and the changing timeline.
The 2026 Integrated System Plan gives the public another chance to review what OPPD is planning and respond before decisions are final.
The ISP brings together big decisions about OPPD's future power system. Open each topic to see the decision, considerations, and impact.
OPPD is modeling different growth scenarios, including how quickly large new customers may increase the amount of electricity they need. Demand projections play a huge role in determining how much new power generation to build, because the Southwest Power Pool’s resource requirements are based on the utility’s actual peak load.
Build too little and the system may not have enough capacity when demand rises. Build too much, too soon, and customers can end up paying for resources that may not be needed.
OPPD says its power needs are growing much faster than they were a few years ago — 2,400% more annually. Large new customers, primarily data centers, are a major part of that increase. According to OPPD figures reported by Nebraska Public Media, data centers used 1% of electricity sold by the utility back in 2018. As of 2024, data centers used 21% of the electricity sold and are expected to account for 41% of sales by 2035.
The ISP is comparing different mixes of resources, including generation from fossil fuels like coal and gas, renewable energy, storage, and options that reduce or shift customer demand.
Different resources come with different costs, construction timelines, fuel needs, operating characteristics and environmental impacts.
These choices will shape OPPD’s energy mix for years and are directly connected to what happens at North Omaha Coal Station and what new resources are built elsewhere.
OPPD compares the cost of different resource options, including fuel, purchased power, transmission and other system needs.
Different choices create costs at different times. Building something new can require a large upfront investment, while keeping older resources can carry ongoing fuel, maintenance, and other costs.
These choices affect OPPD’s finances and customer rates, especially during a period of major investment and rising system costs.
OPPD’s board committed to reaching net-zero carbon emissions by 2050. The ISP will determine what needs to change for OPPD to stay on a path toward that net-zero goal.
Shortly after the OPPD Board set its net zero by 2050 target, OPPD published “Pathways to Decarbonization”, a report done in partnership with the consulting firm E3, which found that “OPPD can achieve net zero carbon while balancing affordability and reliability.” OPPD says replacing or reducing fossil generation requires significant investment in new generation, transmission, storage, and other system resources. Delaying those investments keeps existing fossil plants operating longer and extends the carbon pollution that comes with them.
If OPPD falls behind, coal and gas stay in the system longer and more carbon pollution continues. Every delay leaves less time to meet the board’s own 2050 commitment.
OPPD uses computer modeling to test different ways the region could meet future electricity needs. OPPD feeds the model assumptions about population growth, large new customers, weather, existing power plants, costs, transmission limits and reliability rules. The model then tests different combinations of resources to see what could meet the projected need. These results help show which options OPPD may consider as it plans for the next decade.
OPPD says demand is rising quickly, and data centers are the largest industrial customer group driving that increase. That growth is one reason OPPD is planning for more generation and transmission in the years ahead.
OPPD’s modeling looks at costs over time, including building new resources, fuel, purchased power and operating the system. That means an option with a larger upfront price can look different when OPPD compares its costs over many years.
OPPD’s current five-year capital plan is about $5 billion, with roughly 60% expected to be financed through debt. An independent credit-rating review from S&P Global says that spending is being driven by demand growth, including large new customers such as data centers, changes to the power supply, and higher regional reserve requirements. The S&P Global credit-rating review notes two risks to OPPD’s credit rating: 1) OPPD is moderately leveraged and 2) OPPD’s power supply remains coal dependent, at 59% of energy in 2024.
Units 1–3 stopped burning coal in 2016 and now operate primarily on natural gas. Units 4 and 5 still burn coal.
OPPD originally planned to end coal operations at Units 4 and 5 by the end of 2023. Its 2021 Integrated Resource Plan still called for ending coal use there as new solar and natural-gas resources came online. When those replacement projects were delayed, OPPD pushed the transition back.
OPPD has cited demand growth, higher reserve requirements, local resource needs, and delays in new generation as reasons North Omaha has remained in service longer. The extension has also drawn sustained public opposition over coal use health and transparency.
OPPD’s board has directed the plan to assume Units 1–3 retire and Units 4 and 5 convert from coal to natural gas. The ISP is examining what generation, transmission, and other system changes would be needed to make that transition possible.
This is bigger than one power plant. These choices around North Omaha affect customer bills, reliability, air quality, neighborhood impacts and Omaha’s growth. What has to happen before coal use actually ends?
The plan is not final. Public feedback comes before the board acts.
You don’t have to be an energy expert to have a say in what happens next. Follow the process, ask questions, show up when decisions are being discussed, and stay connected as new information becomes available.
Tell us what you want to understand. We’ll help find the answer or point you to the right information.
Ask a question →Sign up for OPPD-specific email updates.
Get updates →Find upcoming workshops, board meetings, and other public-comment opportunities.
Find upcoming opportunities →Find primary documents, meeting materials, and other resources related to OPPD’s 2026 ISP.
View documents and sources →
Leave a comment
Share your feedback directly with OPPD through the current ISP public-comment form. Written comments become part of the public input considered with the final plan before it is submitted to the federal agency that oversees OPPD’s hydropower agreement.
Leave a comment →Need help commenting?
Not sure where to start or what makes a useful public comment? Reach out and someone from our team can help you understand the process and prepare your own comment.
Get help commenting →