Omaha Public Power District (OPPD) is finalizing its 2026 Integrated System Plan (ISP).

OPPD is public power. Public input is part of what happens next.
Learn what’s in the plan, what’s changing, and how to get involved.

How did we get here?

OPPD’s plans have changed more than once. Deadlines moved, electricity needs grew rapidly, and North Omaha Coal Station (NOS) stayed in service longer than planned.

What is the Integrated System Plan (ISP)?

The ISP brings together big decisions about OPPD's future power system. Open each topic to see the decision, considerations, and impact.

What does Omaha need to power the next decade?

OPPD uses computer modeling to test different ways the region could meet future electricity needs. OPPD feeds the model assumptions about population growth, large new customers, weather, existing power plants, costs, transmission limits and reliability rules. The model then tests different combinations of resources to see what could meet the projected need. These results help show which options OPPD may consider as it plans for the next decade.

Demand is growing fast.

OPPD says demand is rising quickly, and data centers are the largest industrial customer group driving that increase. That growth is one reason OPPD is planning for more generation and transmission in the years ahead.

Graph showing OPPD electricity demand by customer type from 2010 through projected 2035. Data-center electricity demand rises sharply while residential, commercial, and non-data-center industrial demand remain comparatively steady.
21% → 41% Data centers’ share of OPPD electricity sales, 2024 to projected 2035.
Data-center demand rises faster than every other customer type. Residential, commercial, and non-data-center industrial demand remain comparatively steady in OPPD’s projection.
Graphic published by Nebraska Public Media and attributed to OPPD.

Cost isn’t just the price to build something.

OPPD’s modeling looks at costs over time, including building new resources, fuel, purchased power and operating the system. That means an option with a larger upfront price can look different when OPPD compares its costs over many years.

OPPD is planning a major building boom.

OPPD’s current five-year capital plan is about $5 billion, with roughly 60% expected to be financed through debt. An independent credit-rating review from S&P Global says that spending is being driven by demand growth, including large new customers such as data centers, changes to the power supply, and higher regional reserve requirements. The S&P Global credit-rating review notes two risks to OPPD’s credit rating: 1) OPPD is moderately leveraged and 2) OPPD’s power supply remains coal dependent, at 59% of energy in 2024.

What happens next at North Omaha Coal Station?

North Omaha is still burning coal.

Units 1–3 stopped burning coal in 2016 and now operate primarily on natural gas. Units 4 and 5 still burn coal.

Coal use was supposed to end by 2023.

OPPD originally planned to end coal operations at Units 4 and 5 by the end of 2023. Its 2021 Integrated Resource Plan still called for ending coal use there as new solar and natural-gas resources came online. When those replacement projects were delayed, OPPD pushed the transition back.

Why the timeline changed.

OPPD has cited demand growth, higher reserve requirements, local resource needs, and delays in new generation as reasons North Omaha has remained in service longer. The extension has also drawn sustained public opposition over coal use health and transparency.

What the 2026 ISP assumes now.

OPPD’s board has directed the plan to assume Units 1–3 retire and Units 4 and 5 convert from coal to natural gas. The ISP is examining what generation, transmission, and other system changes would be needed to make that transition possible.

This is bigger than one power plant. These choices around North Omaha affect customer bills, reliability, air quality, neighborhood impacts and Omaha’s growth. What has to happen before coal use actually ends?

Public feedback is open.

The plan is not final. Public feedback comes before the board acts.

Get involved.

The official ISP public-comment period has closed, but the process isn’t over. Tell us what you’re thinking, follow the process, and stay connected as OPPD moves toward its final plan.

What should OPPD know?

Share your perspective with Conservation Nebraska. We may use what we hear to inform our participation in upcoming meetings and future OPPD work.

Share your perspective →

What happens next?

The final ISP workshop is Nov. 23, with another opportunity for public comment. Follow upcoming meetings here.

See upcoming meetings →

Ask a question

Tell us what you want to understand. We’ll help find the answer or point you to the right information.

Ask a question →

Read the fine print

Find primary documents, meeting materials, and other resources related to OPPD’s 2026 ISP.

View documents and sources →